Schedule
43 months: August 2014 thru February 2018 (Total Projected Project Duration)
31 months: June 2015 thru January 2018 (Projected Construction Duration)
Budget
$137 million (Total Project Budget)
$112 million (Projected Construction Budget)
Description
$137 million, 146,000 SF new tower construction and renovation of existing hospital. Includes 90-bed patient tower, new ED waiting room/triage area, new 20,000 SF cancer center, new main entrance building addition, renovation of existing labor/delivery, new waiting room and four-pod clinic, as well as site work, utility plant expansion, and new loading dock.
The Northstar Team
Dan Cates, Project Principal; Chris Viviano, Project Director; Dan O'Connor, Senior Project Manager; Jennifer Ott, Project/Equipment Manager; Denise LaChance, Project/Equipment Manager.